Three shipments of steel arrived Monday and were staged and ready for set up, the crane was set near the sport court and the by end of the day Tuesday …
We’re short!!!
It looks like we have come up a little short in the backfill material and the rains are not making it any better. We are a little more than three …
The Building is really taking shape!
Check out the steel structure it’s really something! Imagine a gym on the top of the highest column.
Basement floor is poured!
Big day today, construction crews were everywhere. Concrete started pouring very early this morning. The basement slab is in! Steel crews were welding done the first floor above grade and …
Capillary Break?
As we prepare to pour the concrete slab tomorrow (1-30-15) you will notice a few things being installed in the basement level. First the crew installs a layer of …
Steel framing level one!
The steel floor framing installed today and went according to plan. Most of the first floor is now installed and tomorrow the concrete team will close in the hole . …
70 Ton Mobile Crane Arrives
The crane arrived this morning around 6a to install the steel and fly concrete forms. It’s a busy day ahead. This crane (or one like it) will make numerous visits …
Busy in the hole… PLUMBING
Plumbers are hard at work with under ground pumps and under slab plumbing. The lower level is below sewer inverts and storm drain infiltration systems, so pumps are planted below …
Busy in the hole…ELECTRICAL
Electricians are hard at work preparing all the under slab conduits and in-wall connections. These large pipes are for the main power supply to the building. Over 1200 amps of …
Getting busy in the hole… CONCRETE
With the steel arriving this morning the crews are busy at work getting ready. Concrete crews are hard at work getting ready for the steel erectors, stripping forms and cleaning …